Job Priority is represented by a 3 digit number. The first digit represents Operation Priority.

  • On selecting Client priority precedence, the second digit represents Client priority and third digit represents Agent priority.
  • On selecting Agent Type priority precedence, the second digit represents Agent priority and third digit represents Client priority.

For a Client

On selecting Client priority precedence, the second digit represents Client priority and third digit represents Agent priority.

Use the following steps to set Client Priority Precedence:

  1. From the CommCell Console toolbar, click Control Panel.

    Under the System section, click Job Management.

  2. Click the Job Priorities tab.
  3. Select Client from the Priority Precedence box.
  4. Click OK.

For an Agent

On selecting Agent Type priority precedence, the second digit represents Agent priority and third digit represents Client priority.

Use the following steps to set Agent Priority Precedence:

  1. From the CommCell Console toolbar, click Control Panel.

    Under the System section, click Job Management.

  2. Click the Job Priorities tab.
  3. Select Agent Type from the Priority Precedence box.
  4. Click OK.

Setting the Priority for a Client

By default, the Job Manager automatically assigns a priority of 6 to all client computers. However, you might want to prioritize them according to your requirements by changing the default values to user-defined values.

Use the following steps to set user-defined client priority:

  1. From the CommCell Browser, right-click the <Client> and select Properties.
  2. Click the Job Configuration tab.
  3. Enter a value in the Job Priority box.

    The lower the value, the higher the priority of the client.

  4. Click OK.

Setting the Priority for an Agent

The Job Manager automatically assigns default priorities to all Agents. However, you might want to prioritize them according to your requirements by changing the default values to user-defined values.

Use the following steps to set user-defined agent priority:

  1. From the CommCell Console toolbar, click Control Panel.

    Under the System section, click Job Management.

  2. Click the Job Priorities tab
  3. Select an Agent Type and enter the priority value in the Priority column.

    The lower the value, the higher the priority of the agent.

  4. Click OK.

Viewing Job Priorities

You can view the priorities assigned to

  • All jobs in the Job Controller window.
  • A specific job by viewing the details of the job.

For All Jobs

You can view the priorities of all jobs in the Job Controller window. By default, the Job Controller window does not display the priorities of running jobs. To view the job priorities for all jobs, you need to enable the Priority column.
Use the following steps to view all job priorities:

  1. From the CommCell Console toolbar, click Job Controller.
  2. In the Job Controller pane, right-click any table header or click the double arrows located on the extreme right to display table menu.
  3. Click Choose Columns and then select Priority.
  4. In the Job Controller window, the Priority column indicates the priority numbers for all jobs listed.

For a Specific Job

You can view the priority assigned to a specific job by viewing the details of the job.

Use the following steps to view priority of a specific job:

  1. From the CommCell Console toolbar, click Job Controller.
  2. In the Job Controller pane, right-click an active job and select Detail.
  3. You can view the Priority of the selected job under the General tab.

Setting the Job Priority

Setting Job Priority allows you to change the priority of a job or a group of jobs. You can use it to prioritize jobs based on your requirements by changing their job priority value.

After changing the job priority, if a higher priority job interrupts another lower priority job for resources, then the Job Manager interrupts the running job and allocates the freed resources to a higher priority job only if Job Preemption is allowed.

For Administration Jobs

You can change the priority of the following administration jobs:

  • Auxiliary Copy
  • Data Verification
  • Information Management
  • Media Refresh
  • Persistent Recovery

The Job Manager automatically assigns a priority of 0 to all the jobs. Therefore, the Job Manager assumes that all jobs have the same priority.

Use the following steps to change the priority of administration jobs:

  1. From the CommCell Console toolbar, click Control Panel.

    Under the System section, click Job Management.

  2. Click the Job Priorities tab
  3. Select a Job Type and enter the priority value in the Priority column.

    The lower the value, the higher the priority of the agent.

  4. Click OK.

For an Active Job

Use the following steps to change the priority of an active job:

  1. From the CommCell Console ribbon, click the Home tab and then click Job Controller.
  2. In the Job Controller window, right-click an active job, and then click Change Priority.
  3. In the Change Job Priority dialog box, enter or select a value (from 0 to 999) in the New Priority box.
  1. Click OK.

For a Group of Active Jobs

Use the following steps to change the priority of an active job:

  1. From the CommCell Console ribbon, click the Home tab and then click Job Controller.
  2. In the Job Controller window, right-click an active job, and then click Change Priority.
  3. In the Change Job Priority dialog box, enter or select a value (from 0 to 999) in the New Priority box.
  1. In Select Jobs pane:
    • Select All Jobs to change the priority of all active jobs.
    • Select All Selected Jobs to change the priority of all highlighted jobs.
    • Select All Jobs for this Client to change the priority of jobs of a particular client and then select the client. You can also change the priority of jobs for a particular agent by selecting the Only Jobs for this Agent Type checkbox and then select the agent.
    • Select All Jobs on this MediaAgent to change the priority of jobs of a particular MediaAgent and then select the MediaAgent.
  2. Click OK.

For an Immediate Job

Use the following steps to change the priority of an immediate job:

  1. From the dialog box of an appropriate operation (such as data protection, data recovery or auxiliary copy) click Advanced.
  2. From the resulting dialog box, click the Startup tab.
  3. Select Change Priority and enter a value (from 0 to 999).
  4. To start the job in a suspended state, select the Startup in suspended state checkbox.
  5. Click OK.

For a Scheduled Job

You can change the priority of data protection jobs after it is scheduled.

Use the following steps to change the priority of a scheduled backup job as an example:

  1. From the CommCell Console, right-click CommServe/Client/Agent/BackupSet and then click View | Schedules.

    If you are at the subclient level, right-click the <Subclient> and click Schedules.

  2. Select a scheduled job, right-click and select Edit from the shortcut menu.
  3. Click Advanced.
  4. From the resulting dialog box, click the Startup tab.
  5. Select Change Priority and enter a value (from 0 to 999).
  6. To start the job in a suspended state, select the Startup in suspended state check box.
  7. Click OK.

Setting the Default Job Priority

You can change the priority of a scheduled job from user-defined value to default value.

Use the following steps to set the default priority for a scheduled job:

  1. From the dialog box of an appropriate operation (such as backup, restore or auxiliary copy) click Advanced.
  2. From the resulting dialog box click the Startup tab.
  3. Select Use Default Priority.
  4. To start the job in a suspended state, select the Startup in suspended state check box.
  5. Click OK.