Pre and Post Processes - Getting Started

Pre and post processes can be configured for Data Protection, Data Recovery and Data Replication operations.

Use the following steps to set up pre and post processes around a backup. This procedure uses the Widows File System agent as an example.

Procedure

  1. From the CommCell Browser, go to Client Computers > client > File System > backup_set.
  2. In the backup set tab in the right pane, right-click the subclient, then click Properties.

    The Subclient Properties dialog box appears.

  3. Click the Pre/Post Process tab.
  4. Configure the pre and post processes:
    • Enter the path to the batch file in the PreBackup process box.
    • Enter the path to the batch file in the PostBackup process box.
  5. Click OK.
  6. In the backup set tab in the right pane, right-click the subclient and click Backup.

    The Backup Options dialog box appears.

  7. Select Full as the backup type and Immediate to run the job immediately.
  8. Click OK.